TY - JOUR
T1 - Use of EPS Geofoam for support of a bridge
AU - Stuedlein, Armin W.
AU - Negussey, Dawit
N1 - Funding Information:
EPS geofoamwas used to fill thevoid within a sheet pile cofferdam abutment to support the bridge superstructure. Performance observations indicated that the geofoamfill may not bein contact with theunderlying foundation soil. Depending on the water levels within the sheet pile cell, the superstructure is supported in part by buoyancy of the EPS fill and in shear resistance along the cofferdam-soil interface. Thermal creep of the EPS geofoamfill was initiated by the heatof hydration within the thick load distribution slab. Subsequent relaxation with heat dissipation further facilitated load transfer to the sheet pile cell and support by skin friction and buoyancy. The construction stage observations suggest a need to study the effects of compressive strength and creep of EPS geofoam under higher temperatures. Overall, post construction observations over 500 days and subsequent biennial bridge inspection reports to date indicate outstanding performance.
Funding Information:
The Buffalo Road replacement bridge performance observation was supported by NYSDOT Transportation Infrastructure Research Consortium (TIRC). Benjamin Beardsley of Erdman Anthony and Associates, Gary Weidman of Wyoming County Highway Department, Geotechnical Engineer Ray Teeter were helpful at various stages of the monitoring project.
PY - 2013
Y1 - 2013
N2 - In much of reported geofoam applications in roadway construction, innovative uses featured approach fills and light weight embankments below rigid or flexible pavement structures. This paper describes a bridge construction that represents a marked departure from conventional practice. EPS geofoam was used to support pre-stressed concrete box beams and composite concrete deck of a single span bridge. The bridge is a replacement of a shorter, steel-girder single-span bridge on spread footings across Oatka Creek in Warsaw, NY. Criteria for the new bridge included a larger span and increased load and hydraulic capacities. Soil borings showed very weak strata extend to large depths, initially suggesting the need for deep foundations to support the new bridge. As an alternative to piles, excavation and replacement of the underlying soil with EPS geofoam was selected to provide a compensated foundation system. This paper describes the construction and post-construction performance monitoring of the bridge. The instrumentation included stress cells, settlement plates, and piezometers. Heat dissipation in the thick early strength concrete of the abutment slabs was monitored, and was inferred as the source of thermally-induced creep. Periodic surveys of the roadway profile were also taken. Subsequent to completion, the bridge and the approaches were inundated during a period of intense rainfall, and successfully withstood the uplift due to buoyancy. Following 10 years of service, the bridge continues to be rated with the highest NYSDOT bridge performance ranking in 2012.
AB - In much of reported geofoam applications in roadway construction, innovative uses featured approach fills and light weight embankments below rigid or flexible pavement structures. This paper describes a bridge construction that represents a marked departure from conventional practice. EPS geofoam was used to support pre-stressed concrete box beams and composite concrete deck of a single span bridge. The bridge is a replacement of a shorter, steel-girder single-span bridge on spread footings across Oatka Creek in Warsaw, NY. Criteria for the new bridge included a larger span and increased load and hydraulic capacities. Soil borings showed very weak strata extend to large depths, initially suggesting the need for deep foundations to support the new bridge. As an alternative to piles, excavation and replacement of the underlying soil with EPS geofoam was selected to provide a compensated foundation system. This paper describes the construction and post-construction performance monitoring of the bridge. The instrumentation included stress cells, settlement plates, and piezometers. Heat dissipation in the thick early strength concrete of the abutment slabs was monitored, and was inferred as the source of thermally-induced creep. Periodic surveys of the roadway profile were also taken. Subsequent to completion, the bridge and the approaches were inundated during a period of intense rainfall, and successfully withstood the uplift due to buoyancy. Following 10 years of service, the bridge continues to be rated with the highest NYSDOT bridge performance ranking in 2012.
UR - http://www.scopus.com/inward/record.url?scp=84887280492&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84887280492&partnerID=8YFLogxK
M3 - Article
AN - SCOPUS:84887280492
SN - 0895-0563
SP - 334
EP - 345
JO - Geotechnical Special Publication
JF - Geotechnical Special Publication
IS - 230
ER -