TY - JOUR
T1 - Survey Comparing Critical Path Method, Last Planner System, and Location-Based Techniques
AU - Olivieri, Hylton
AU - Seppänen, Olli
AU - Alves, Thais Da C.L.
AU - Scala, Natalie M.
AU - Schiavone, Vincent
AU - Liu, Min
AU - Granja, Ariovaldo Denis
N1 - Publisher Copyright:
© 2019 American Society of Civil Engineers.
PY - 2019/12/1
Y1 - 2019/12/1
N2 - In construction, the most relevant systems used for project management (PM) and project production management (PPM) in the planning and control phases are critical path method (CPM), last planner system (LPS), and location-based techniques (LB). Studies have addressed these systems, mostly in isolated fashions. This study aims to compare and contrast their use in terms of PM and PPM and clarify industry benefits in order to eliminate potential misunderstandings about their use. A survey was administered to construction professionals in Brazil, China, Finland, and the United States. No single system addresses all needs of PM and PPM. CPM is the dominant system when considering the following characteristics: primary industry types, type of organization, size of organization, professional position within the organization, and area of work. Contributions to knowledge include that CPM is a contract requirement with perceived benefits associated with critical path analysis; LB and LPS have perceived benefits regarding continuous flow and use of resources, treatment of interferences, and improving production control. All systems were found to have a similar level of benefits for management of contracts, delay and change, and evaluation of the root causes of delays. The industry can benefit from aligning project scheduling methods with project needs.
AB - In construction, the most relevant systems used for project management (PM) and project production management (PPM) in the planning and control phases are critical path method (CPM), last planner system (LPS), and location-based techniques (LB). Studies have addressed these systems, mostly in isolated fashions. This study aims to compare and contrast their use in terms of PM and PPM and clarify industry benefits in order to eliminate potential misunderstandings about their use. A survey was administered to construction professionals in Brazil, China, Finland, and the United States. No single system addresses all needs of PM and PPM. CPM is the dominant system when considering the following characteristics: primary industry types, type of organization, size of organization, professional position within the organization, and area of work. Contributions to knowledge include that CPM is a contract requirement with perceived benefits associated with critical path analysis; LB and LPS have perceived benefits regarding continuous flow and use of resources, treatment of interferences, and improving production control. All systems were found to have a similar level of benefits for management of contracts, delay and change, and evaluation of the root causes of delays. The industry can benefit from aligning project scheduling methods with project needs.
KW - Construction
KW - Critical path method
KW - Last planner system
KW - Location-based systems
KW - Scheduling
UR - http://www.scopus.com/inward/record.url?scp=85072785714&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=85072785714&partnerID=8YFLogxK
U2 - 10.1061/(ASCE)CO.1943-7862.0001644
DO - 10.1061/(ASCE)CO.1943-7862.0001644
M3 - Article
AN - SCOPUS:85072785714
SN - 0733-9364
VL - 145
JO - Journal of Construction Engineering and Management
JF - Journal of Construction Engineering and Management
IS - 12
M1 - 04019077
ER -