Project scheduling with discounted cash flows and progress payments

Burak Kazaz, Canan Sepil

Research output: Contribution to journalArticlepeer-review

35 Scopus citations

Abstract

In all large scale projects, there correspond cash flows that incur throughout the life of the project. The scheduling of these projects to maximize the present value of the cash flows has been a topic of recent research. The basic assumption of earlier research is that the cash flows are mainly associated with some events of the project and they occur at the event realization times. However, in several real life projects, the cash inflows do not occur at the event realization times, rather they occur at the end of some time periods, like months, as progress payments. In this article, maximizing the present value of the cash flows in such projects is considered and a mixed-integer formulation of the problem is presented. In this formulation, activity profit curves are defined and used. Computational experience on some randomly generated test problems provides promising results especially when the Benders Decomposition technique is employed for solving the problem.

Original languageEnglish (US)
Pages (from-to)1262-1272
Number of pages11
JournalJournal of the Operational Research Society
Volume47
Issue number10
DOIs
StatePublished - Oct 1996
Externally publishedYes

Keywords

  • Benders decomposition
  • Mixed integer programming
  • Project scheduling

ASJC Scopus subject areas

  • Statistics, Probability and Uncertainty
  • Modeling and Simulation
  • Strategy and Management
  • Management Science and Operations Research

Fingerprint

Dive into the research topics of 'Project scheduling with discounted cash flows and progress payments'. Together they form a unique fingerprint.

Cite this