TY - GEN
T1 - Causes and penalties of variation - A case study of a concrete slab prefabrication shop
AU - Wang, Chao
AU - Hsiang, Simon
AU - Liu, Min
PY - 2011
Y1 - 2011
N2 - Concrete precast plants require strict control over and adherence to the timing and sequence of operations. Variation for this research is divided into the variation in task starting time (the difference between the planned and the actual starting time) and the variation in task duration (the difference between the planned and the actual task duration). This study determined causes of variation in task starting time and duration of precast concrete slab production tasks and used STROBOSCOPE simulation techniques to demonstrate the penalties associated with not reducing variation, which are 1) overtime, 2) Work in Progress (WIP) increase, 3) cost overrun, and 4) labor productivity decrease. It was found that simply taking managerial actions, such as keeping workers waiting or busy, is insufficient for managing variation and effort should be put to reduce variations and make plan more reliable. The results could help prefabricators to understand the causes and penalties of variation, which is the starting point of attacking and reducing variations.
AB - Concrete precast plants require strict control over and adherence to the timing and sequence of operations. Variation for this research is divided into the variation in task starting time (the difference between the planned and the actual starting time) and the variation in task duration (the difference between the planned and the actual task duration). This study determined causes of variation in task starting time and duration of precast concrete slab production tasks and used STROBOSCOPE simulation techniques to demonstrate the penalties associated with not reducing variation, which are 1) overtime, 2) Work in Progress (WIP) increase, 3) cost overrun, and 4) labor productivity decrease. It was found that simply taking managerial actions, such as keeping workers waiting or busy, is insufficient for managing variation and effort should be put to reduce variations and make plan more reliable. The results could help prefabricators to understand the causes and penalties of variation, which is the starting point of attacking and reducing variations.
KW - Causes
KW - Concrete slab prefabrication
KW - Lean construction
KW - Penalties
KW - Variation
UR - http://www.scopus.com/inward/record.url?scp=84876751993&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84876751993&partnerID=8YFLogxK
M3 - Conference contribution
AN - SCOPUS:84876751993
SN - 9781622768233
T3 - 19th Annual Conference of the International Group for Lean Construction 2011, IGLC 2011
SP - 220
EP - 229
BT - 19th Annual Conference of the International Group for Lean Construction 2011, IGLC 2011
T2 - 19th Annual Conference of the International Group for Lean Construction 2011, IGLC 2011
Y2 - 13 July 2011 through 15 July 2011
ER -